version: "1.0.0" name: "4d-simulation" description: "Create 4D construction simulations by linking BIM elements to project schedules. Generate time-based visualizations, sequence analysis, and construction phasing with Gantt integration." homepage: "https://datadrivenconstruction.io" metadata: {"openclaw": {"emoji": "🎬", "os": ["darwin", "linux", "win32"], "homepage": "https://datadrivenconstruction.io", "requires": {"bins": ["python3"]}}}
4D Simulation for Construction
Overview
Based on DDC methodology (Chapter 3.3), this skill implements 4D BIM simulations - linking 3D model elements to the 4th dimension: time. Visualize construction sequences, detect scheduling conflicts, and optimize work phasing.
Book Reference: "4D, 6D-8D и расчет CO2" / "4D-8D BIM and CO2 Calculation"
"4D моделирование позволяет визуализировать последовательность строительства и выявлять конфликты на этапе планирования."— DDC Book, Chapter 3.3
Quick Start
python
import pandas as pdfrom datetime import datetime, timedelta# BIM elements with schedule dataelements = pd.DataFrame({'ElementId': ['E001', 'E002', 'E003', 'E004'],'Category': ['Foundation', 'Column', 'Beam', 'Slab'],'Level': ['Level 0', 'Level 1', 'Level 1', 'Level 1'],'Start_Date': ['2024-01-01', '2024-01-15', '2024-02-01', '2024-02-15'],'End_Date': ['2024-01-14', '2024-01-31', '2024-02-14', '2024-02-28'],'Phase': ['Structure', 'Structure', 'Structure', 'Structure']})elements['Start_Date'] = pd.to_datetime(elements['Start_Date'])elements['End_Date'] = pd.to_datetime(elements['End_Date'])elements['Duration_Days'] = (elements['End_Date'] - elements['Start_Date']).dt.days# Get elements active on a specific datetarget_date = pd.to_datetime('2024-01-20')active_elements = elements[(elements['Start_Date'] <= target_date) &(elements['End_Date'] >= target_date)]print(f"Elements under construction on {target_date.date()}:")print(active_elements[['ElementId', 'Category']])
4D Data Model
Schedule-Element Linking
python
import pandas as pdimport numpy as npfrom datetime import datetime, timedeltafrom typing import List, Dict, Optionalclass ScheduleElementLinker:"""Link BIM elements to schedule activities"""def __init__(self, elements_df: pd.DataFrame, schedule_df: pd.DataFrame):self.elements = elements_df.copy()self.schedule = schedule_df.copy()self.links = pd.DataFrame()def auto_link_by_category(self, mapping: Dict[str, str]):"""Auto-link elements to activities by category mappingArgs:mapping: Dict mapping element categories to activity namese.g., {'Wall': 'Structural Walls', 'Slab': 'Floor Construction'}"""links = []for category, activity_name in mapping.items():# Find elements of this categorycategory_elements = self.elements[self.elements['Category'] == category]['ElementId'].tolist()# Find matching activityactivity = self.schedule[self.schedule['Activity'].str.contains(activity_name, case=False)]if not activity.empty and category_elements:for elem_id in category_elements:links.append({'ElementId': elem_id,'ActivityId': activity.iloc[0]['ActivityId'],'Activity': activity.iloc[0]['Activity'],'Start_Date': activity.iloc[0]['Start_Date'],'End_Date': activity.iloc[0]['End_Date']})self.links = pd.DataFrame(links)return self.linksdef auto_link_by_level(self):"""Auto-link elements based on level and construction sequence"""# Get unique levels in orderlevels = sorted(self.elements['Level'].unique())links = []for i, level in enumerate(levels):level_elements = self.elements[self.elements['Level'] == level]# Find activity for this levellevel_activity = self.schedule[self.schedule['Activity'].str.contains(level, case=False)]if not level_activity.empty:for _, elem in level_elements.iterrows():links.append({'ElementId': elem['ElementId'],'ActivityId': level_activity.iloc[0]['ActivityId'],'Activity': level_activity.iloc[0]['Activity'],'Start_Date': level_activity.iloc[0]['Start_Date'],'End_Date': level_activity.iloc[0]['End_Date']})self.links = pd.DataFrame(links)return self.linksdef manual_link(self, element_id: str, activity_id: str):"""Manually link element to activity"""element = self.elements[self.elements['ElementId'] == element_id]activity = self.schedule[self.schedule['ActivityId'] == activity_id]if element.empty or activity.empty:raise ValueError("Element or activity not found")new_link = pd.DataFrame([{'ElementId': element_id,'ActivityId': activity_id,'Activity': activity.iloc[0]['Activity'],'Start_Date': activity.iloc[0]['Start_Date'],'End_Date': activity.iloc[0]['End_Date']}])self.links = pd.concat([self.links, new_link], ignore_index=True)return self.linksdef get_linked_elements(self):"""Get elements with schedule data"""return self.elements.merge(self.links[['ElementId', 'ActivityId', 'Start_Date', 'End_Date']],on='ElementId',how='left')
4D Simulation Engine
python
class Simulation4D:"""4D construction simulation engine"""def __init__(self, linked_elements: pd.DataFrame):self.elements = linked_elements.copy()self.elements['Start_Date'] = pd.to_datetime(self.elements['Start_Date'])self.elements['End_Date'] = pd.to_datetime(self.elements['End_Date'])self.project_start = self.elements['Start_Date'].min()self.project_end = self.elements['End_Date'].max()def get_state_at_date(self, target_date: datetime) -> pd.DataFrame:"""Get element states at a specific date"""target = pd.to_datetime(target_date)# Determine state for each elementconditions = [target < self.elements['Start_Date'], # Not started(self.elements['Start_Date'] <= target) & (target <= self.elements['End_Date']), # In progresstarget > self.elements['End_Date'] # Completed]choices = ['not_started', 'in_progress', 'completed']self.elements['State'] = np.select(conditions, choices, default='unknown')return self.elements.copy()def generate_timeline(self, interval_days: int = 7) -> List[Dict]:"""Generate timeline snapshots"""timeline = []current_date = self.project_startwhile current_date <= self.project_end:state = self.get_state_at_date(current_date)snapshot = {'date': current_date,'not_started': len(state[state['State'] == 'not_started']),'in_progress': len(state[state['State'] == 'in_progress']),'completed': len(state[state['State'] == 'completed']),'total': len(state)}snapshot['progress_pct'] = (snapshot['completed'] / snapshot['total']) * 100timeline.append(snapshot)current_date += timedelta(days=interval_days)return timelinedef get_elements_in_progress(self, target_date: datetime) -> pd.DataFrame:"""Get elements currently under construction"""state = self.get_state_at_date(target_date)return state[state['State'] == 'in_progress']def analyze_construction_sequence(self) -> pd.DataFrame:"""Analyze construction sequence by category and level"""sequence = self.elements.groupby(['Level', 'Category']).agg({'Start_Date': 'min','End_Date': 'max','ElementId': 'count'}).rename(columns={'ElementId': 'Element_Count'})sequence['Duration_Days'] = (sequence['End_Date'] - sequence['Start_Date']).dt.dayssequence = sequence.sort_values('Start_Date').reset_index()return sequencedef detect_parallel_work(self) -> pd.DataFrame:"""Detect work happening in parallel"""dates = pd.date_range(self.project_start, self.project_end, freq='D')parallel_work = []for date in dates:state = self.get_state_at_date(date)in_progress = state[state['State'] == 'in_progress']if len(in_progress) > 1:categories = in_progress['Category'].unique().tolist()levels = in_progress['Level'].unique().tolist()parallel_work.append({'date': date,'parallel_count': len(in_progress),'categories': ', '.join(categories),'levels': ', '.join(levels)})return pd.DataFrame(parallel_work)
Gantt Chart Integration
Gantt Chart Generator
python
import matplotlib.pyplot as pltimport matplotlib.dates as mdatesfrom matplotlib.patches import Patchclass GanttChartGenerator:"""Generate Gantt charts for 4D simulation"""def __init__(self, elements: pd.DataFrame):self.elements = elements.copy()self.colors = {'Foundation': '#8B4513','Column': '#4169E1','Beam': '#228B22','Slab': '#DC143C','Wall': '#FF8C00','Roof': '#9932CC','MEP': '#20B2AA','Finishes': '#FFD700'}def create_gantt(self, group_by='Category', figsize=(14, 8)):"""Create Gantt chart grouped by specified column"""fig, ax = plt.subplots(figsize=figsize)# Group elementsgroups = self.elements.groupby(group_by)y_pos = 0y_labels = []legend_elements = []for group_name, group_df in groups:color = self.colors.get(group_name, '#808080')for _, row in group_df.iterrows():start = row['Start_Date']duration = (row['End_Date'] - row['Start_Date']).daysax.barh(y_pos, duration, left=start, height=0.6,color=color, alpha=0.8, edgecolor='black', linewidth=0.5)y_pos += 1y_labels.append(group_name)legend_elements.append(Patch(facecolor=color, label=group_name))# Formattingax.set_yticks(range(len(self.elements)))ax.set_yticklabels(self.elements['ElementId'])ax.set_xlabel('Date')ax.set_title('Construction Schedule - Gantt Chart', fontsize=14, fontweight='bold')# Date formattingax.xaxis.set_major_formatter(mdates.DateFormatter('%Y-%m-%d'))ax.xaxis.set_major_locator(mdates.WeekdayLocator(interval=2))plt.xticks(rotation=45)# Legendax.legend(handles=legend_elements, loc='upper right')# Gridax.grid(axis='x', alpha=0.3)plt.tight_layout()return figdef create_level_gantt(self, figsize=(14, 10)):"""Create Gantt chart grouped by level"""fig, ax = plt.subplots(figsize=figsize)levels = sorted(self.elements['Level'].unique())for i, level in enumerate(levels):level_elements = self.elements[self.elements['Level'] == level]for _, row in level_elements.iterrows():color = self.colors.get(row['Category'], '#808080')start = row['Start_Date']duration = (row['End_Date'] - row['Start_Date']).daysax.barh(i, duration, left=start, height=0.4,color=color, alpha=0.8, edgecolor='black', linewidth=0.5)ax.set_yticks(range(len(levels)))ax.set_yticklabels(levels)ax.set_xlabel('Date')ax.set_ylabel('Building Level')ax.set_title('Construction Sequence by Level', fontsize=14, fontweight='bold')ax.xaxis.set_major_formatter(mdates.DateFormatter('%Y-%m-%d'))plt.xticks(rotation=45)# Add legendlegend_patches = [Patch(color=c, label=cat) for cat, c in self.colors.items()if cat in self.elements['Category'].values]ax.legend(handles=legend_patches, loc='upper right')plt.tight_layout()return figdef create_progress_chart(self, timeline: List[Dict], figsize=(12, 6)):"""Create S-curve progress chart"""df = pd.DataFrame(timeline)fig, ax = plt.subplots(figsize=figsize)ax.plot(df['date'], df['progress_pct'], 'b-', linewidth=2, label='Progress')ax.fill_between(df['date'], 0, df['progress_pct'], alpha=0.3)# Add milestones at 25%, 50%, 75%, 100%for milestone in [25, 50, 75, 100]:ax.axhline(y=milestone, color='gray', linestyle='--', alpha=0.5)ax.text(df['date'].iloc[0], milestone + 2, f'{milestone}%',fontsize=9, color='gray')ax.set_xlabel('Date')ax.set_ylabel('Progress (%)')ax.set_title('Project S-Curve', fontsize=14, fontweight='bold')ax.set_ylim(0, 105)ax.xaxis.set_major_formatter(mdates.DateFormatter('%Y-%m-%d'))plt.xticks(rotation=45)plt.tight_layout()return fig
Sequence Analysis
Construction Sequence Optimizer
python
class SequenceAnalyzer:"""Analyze and optimize construction sequences"""def __init__(self, elements: pd.DataFrame):self.elements = elements.copy()self.dependencies = []def add_dependency(self, predecessor: str, successor: str, lag_days: int = 0):"""Add dependency between elements"""self.dependencies.append({'predecessor': predecessor,'successor': successor,'lag_days': lag_days})def check_sequence_violations(self) -> List[Dict]:"""Check for sequence violations"""violations = []for dep in self.dependencies:pred = self.elements[self.elements['ElementId'] == dep['predecessor']]succ = self.elements[self.elements['ElementId'] == dep['successor']]if pred.empty or succ.empty:continuepred_end = pred.iloc[0]['End_Date']succ_start = succ.iloc[0]['Start_Date']required_start = pred_end + timedelta(days=dep['lag_days'])if succ_start < required_start:violations.append({'predecessor': dep['predecessor'],'successor': dep['successor'],'predecessor_end': pred_end,'successor_start': succ_start,'required_start': required_start,'violation_days': (required_start - succ_start).days})return violationsdef check_spatial_conflicts(self) -> List[Dict]:"""Check for spatial conflicts (same location, same time)"""conflicts = []# Group by location (Level + Zone if available)location_col = 'Level'for location, group in self.elements.groupby(location_col):if len(group) < 2:continue# Check for overlapping workfor i, row1 in group.iterrows():for j, row2 in group.iterrows():if i >= j:continue# Check date overlapoverlap = (row1['Start_Date'] <= row2['End_Date'] androw2['Start_Date'] <= row1['End_Date'])if overlap:conflicts.append({'location': location,'element1': row1['ElementId'],'element1_category': row1['Category'],'element2': row2['ElementId'],'element2_category': row2['Category'],'overlap_start': max(row1['Start_Date'], row2['Start_Date']),'overlap_end': min(row1['End_Date'], row2['End_Date'])})return conflictsdef calculate_critical_path(self) -> List[str]:"""Calculate critical path (simplified)"""# Build dependency graphgraph = {}for elem in self.elements['ElementId']:graph[elem] = {'predecessors': [],'duration': 0}for dep in self.dependencies:if dep['successor'] in graph:graph[dep['successor']]['predecessors'].append(dep['predecessor'])# Calculate durationsfor _, row in self.elements.iterrows():if row['ElementId'] in graph:graph[row['ElementId']]['duration'] = (row['End_Date'] - row['Start_Date']).days# Find longest path (simplified critical path)def longest_path(node, memo={}):if node in memo:return memo[node]if not graph[node]['predecessors']:return graph[node]['duration']max_pred = max(longest_path(pred, memo) for pred in graph[node]['predecessors'])memo[node] = max_pred + graph[node]['duration']return memo[node]# Get all path lengthspath_lengths = {elem: longest_path(elem) for elem in graph.keys()}# Critical path elementsmax_length = max(path_lengths.values())critical = [elem for elem, length in path_lengths.items() if length == max_length]return critical
Export and Integration
python
def export_4d_schedule(elements: pd.DataFrame, output_path: str):"""Export 4D schedule to Excel with multiple views"""with pd.ExcelWriter(output_path, engine='openpyxl') as writer:# Full scheduleelements.to_excel(writer, sheet_name='Schedule', index=False)# By levellevel_summary = elements.groupby('Level').agg({'ElementId': 'count','Start_Date': 'min','End_Date': 'max'}).rename(columns={'ElementId': 'Element_Count'})level_summary['Duration_Days'] = (level_summary['End_Date'] - level_summary['Start_Date']).dt.dayslevel_summary.to_excel(writer, sheet_name='By_Level')# By categorycat_summary = elements.groupby('Category').agg({'ElementId': 'count','Start_Date': 'min','End_Date': 'max'}).rename(columns={'ElementId': 'Element_Count'})cat_summary.to_excel(writer, sheet_name='By_Category')return output_path
Quick Reference
| Concept | Description | |
|---|---|---|
| 4D = 3D + Time | BIM model linked to schedule | |
| Activity | Scheduled work item | |
| Element State | not_started / in_progress / completed | |
| Critical Path | Longest sequence determining project duration |
Resources
- Book: "Data-Driven Construction" by Artem Boiko, Chapter 3.3
- Website: https://datadrivenconstruction.io
Next Steps
- See
gantt-chartfor schedule visualization - See
co2-estimationfor 6D (sustainability) analysis - See
clash-detection-analysisfor 4D conflict detection