Trusted Publisher100/100version: "1.0.0" name: dev-sprint description: How to run a development sprint in Capsem. Use when starting a new feature, multi-step task, or any work that spans multiple changes. Covers sprint planning, progress tracking, changelog discipline, commit strategy, testing gates, and release. Enforces the workflow -- plan first, track progress, commit at functional milestones, always finish with testing.
Development Sprint
Every non-trivial task follows this workflow. No shortcuts.
1. Plan
Create a sprint directory and write the plan before touching code:
mkdir -p sprints/<sprint-name>
Write sprints/<sprint-name>/plan.md:
- What we're building and why
- Key decisions and trade-offs
- Files to create/modify
- Dependencies and ordering
- What "done" looks like
- The testing proof matrix for each functional slice: unit/contract,
functional, adversarial, E2E/VM, telemetry, and performance
The plan is a living document. Update it as the sprint evolves -- crossed-out items, new discoveries, changed approach. The plan is evidence of thinking, not a contract.
2. Track
Create sprints/<sprint-name>/tracker.md as a checklist:
# Sprint: <name>## Tasks-[x] Task 1 -- description-[x] Task 2 -- description-[ ] Task 3 -- description-[ ] Testing gate-[ ] Changelog-[ ] Commit## Notes-Discovery: found that X needs Y-Changed approach: Z instead of W because...## Coverage Ledger-Unit/contract:-Functional:-Adversarial:-E2E/VM:-Telemetry:-Performance:-Missing/deferred:
Update the tracker as you go. Check items off. Add notes about surprises, blockers, and changed approaches. This is your scratchpad -- future you (or the next conversation) reads this to understand what happened.
For every functional milestone, keep the coverage ledger current. Do not mark a task complete with only implementation notes and a command list. Name the actual tests or manual VM checks that prove the feature, and name the missing categories honestly. A benchmark can prove performance, not functional correctness. A Rust unit suite can prove contracts, not the user-visible VM path.
3. Build
Write code. Follow the project skills:
/dev-debuggingfor bug investigation (reproduce first, diagnose, then fix)/dev-testingfor TDD (write test, see it fail, implement, refactor)/dev-rust-patternsfor async/cross-compile patterns/dev-mitm-proxy,/dev-mcpfor subsystem-specific guidance
4. Commit at functional milestones
Do NOT commit after every file edit. Do NOT batch everything into one giant commit at the end. Commit when:
- A logical unit of work is complete and functional
- Tests pass for that unit
- The codebase is in a good state (not half-refactored)
- The tracker has an explicit coverage ledger for that milestone,
including missing/deferred functional, adversarial, E2E/VM, telemetry, or performance coverage
Each commit should:
- Be self-contained (revertable without breaking things)
- Include its CHANGELOG.md entry
- Stage files explicitly (no
git add -A) - Use conventional messages:
feat:,fix:,chore:,docs:
Bad: 20 tiny commits for each file touched. Also bad: 1 commit with 40 files after hours of work. Good: 3-5 commits per sprint, each representing a meaningful milestone.
5. Changelog
Update CHANGELOG.md under ## [Unreleased] as part of each commit. Write from the user's perspective:
- Added: new capability
- Changed: modified behavior
- Fixed: bug fix
- Security: security improvement
Do not batch changelog entries at the end. Each commit carries its own entry.
6. Testing gate
Every sprint ends with testing. No exceptions.
just test # ALL tests: unit + integration + cross-compile + frontend + benchjust run "capsem-doctor" # VM smoke test
If the sprint touched telemetry:
just inspect-session # Verify telemetry after a real session
If tests fail, fix them before considering the sprint done. See /dev-debugging for the methodology.
The testing gate must cover the story, not just the code that was easiest to test. For each shipped behavior, verify:
- Unit/contract tests for the smallest meaningful logic boundary
- Functional tests through the production-facing API
- Adversarial tests for malformed input, denials, timeouts, races, and leak prevention
- E2E/VM tests for the real user path when the behavior crosses a VM, CLI, MCP, service, telemetry, or network boundary
- Session DB or external-state checks when the behavior claims auditability
- Benchmarks only when performance is part of the claim
If one of those is missing, keep the sprint open or record the exact debt in the tracker with a follow-up task. Do not bury the gap in prose like "covered later"; make it visible.
7. Clean up
- Verify no debug prints, TODO comments, or temporary hacks remain
- Run
/simplifyif significant code was written
Sprint artifacts
sprints/<sprint-name>/plan.md What we're building, key decisionstracker.md Checklist + noteschangelog.md Draft changelog entries (optional, can go straight to CHANGELOG.md)
The sprints/ directory is git-tracked. Sprint plans and trackers are committed alongside the code they describe.
Meta sprints (sub-sprints)
Large efforts use a meta sprint with sub-sprints. The meta sprint has a MASTER.md that tracks overall status, and each sub-sprint gets its own file:
sprints/<meta-name>/MASTER.md Overall status table, phase groupings, just recipesT0-infrastructure.md Sub-sprint 0T1-service-unit-tests.md Sub-sprint 1T2-process-unit-tests.md Sub-sprint 2...implementation-tasks.md What code must change for tests to pass (optional)tracker.md Active execution tracker (current sub-sprint progress)
MASTER.md is the entry point. It contains:
- A status table with every sub-sprint, its status (Done / In Progress / Not Started), test count, and dependencies
- Phase groupings (Foundation, Integration, E2E, etc.)
- Relevant just recipes
When executing a meta sprint, create a tracker.md for the active work. Update MASTER.md status as sub-sprints complete.
Anti-patterns
- No plan: jumping straight to code leads to rework and wrong abstractions
- Commit per file: noise in git history, impossible to revert cleanly
- One mega commit: can't bisect, can't review, can't cherry-pick
- Skip testing: "I'll test later" means "I'll ship bugs now"
- Stale tracker: if the tracker doesn't match reality, it's useless
- Benchmark-as-proof: performance numbers do not prove the feature is correct
- Silent coverage debt: missing E2E, functional, or adversarial tests must be named before a milestone can be called done