version: "1.0.0" name: principle-postmortem description: Postmortem principles — blameless culture, root cause analysis (5 Whys, Fishbone), incident document structure, MTTD/MTTR metrics. Auto-load when running a blameless review, facilitating RCA, tracking action items after an outage, or improving incident response processes.


<!-- preload-canary: SWB-PRELOAD-PRINCIPLE-POSTMORTEM -->

Postmortem

Incidents are inevitable. A postmortem converts failure into systemic learning — the goal is not to assign blame but to close the gap between what the system can do and what the environment demands. The prevent → detect → learn triad is incomplete without this phase.

Cross-references: swe-workbench:principle-resiliency (prevent), principle-observability#SLI / SLO / Error Budget (detect / MTTD-MTTR framing), principle-release-engineering#Rollback (remediation action items).

Blameless Culture

Blame suppresses signal. When individuals fear punishment, they conceal information, underreport near-misses, and avoid risky-but-necessary work. Blameless postmortems operate from the assumption that everyone acted rationally given the information and tools available to them at the time.

Guiding principles:

  • "The system allowed it" — if a person could cause an outage, the system lacked the guardrails to prevent it. The fix belongs in the system, not the person.
  • Psychological safety — participants must feel safe sharing the full sequence of events, including their own mistakes. Facilitation owns this; interrupt any language that assigns personal fault.
  • Hindsight bias — it is easy to see the right move after the fact. Explicitly reconstruct the information available at each decision point; do not evaluate decisions using information that only became visible later.
  • Counterfactual fairness — "if only they had done X" is only valid if X was a realistic, well-understood option at the time. If X required information no one had, the real gap is in the information architecture.
  • Separate the review from personnel processes — postmortems feed the improvement backlog, not performance reviews.

Root Cause Analysis

A single proximate cause is almost never the full story. Three distinct layers exist:

  • Trigger — the immediate event that precipitated the incident (a deployment, a traffic spike, a configuration change).
  • Condition — the pre-existing state that made the system vulnerable to that trigger (an untested code path, a missing circuit breaker, a stale cache TTL).
  • Root cause — the systemic gap that allowed the condition to persist undetected (absent pre-deploy checklist, no SLO alert on the affected path, no load test in CI).

Fixing only the trigger prevents the exact same incident; fixing the root cause prevents a class of incidents.

5 Whys

Iteratively ask "why did this happen?" until you reach a controllable, systemic factor. Each answer becomes the premise of the next question.

  • Start from the trigger, not the symptom.
  • Stop when the answer is "we had no process / no visibility / no incentive to catch this" — that is a root cause.
  • Document each why-answer pair; the chain is the evidence.
  • Beware shallow stopping: "human error" is almost never a root cause — ask why the error was possible.

Fishbone (Ishikawa)

Use when the incident has multiple, parallel contributing factors that do not form a clean causal chain. Draw a central "spine" (the effect) with branches for contributing factor categories:

  • People — training gaps, handoff failures, role ambiguity.
  • Process — missing runbooks, inadequate on-call rotations, unclear escalation paths.
  • Tooling — alert fatigue, missing dashboards, slow deploy pipelines, inadequate rollback mechanisms.
  • Environment — dependency failures, infrastructure limits, third-party SLA violations.
  • Measurement — absent or lagging metrics, poorly calibrated SLOs, no baseline data.

Each branch can have sub-branches. Fishbone complements 5 Whys: use 5 Whys to drill into the most critical branch found by the Fishbone diagram.

Postmortem Document Structure

Time-box the draft to 24–72 hours after mitigation while memory is fresh.

Required sections, in order:

  • Title + Severity + Status — descriptive title, severity tier (P0–P3 or equivalent), draft/reviewed/closed.
  • Timeline — chronological sequence of events with UTC timestamps: when did the condition begin, when was the incident detected, when were responders paged, when was mitigation applied, when was the incident closed.
  • Impact — who was affected, how many users/requests/dollars, duration. Quantify; avoid vague language.
  • Root cause — one paragraph. Uses the trigger/condition/root-cause framing from above.
  • Contributing factors — list of conditions that compounded the impact or delayed detection.
  • Lessons learned — what went well (do not skip this; it anchors future behavior), what went poorly, where there was luck.
  • Action items — see Action-Item Discipline below.

Action-Item Discipline

"Improve monitoring" is not an action item. An action item is a specific, measurable change assigned to a named owner with a due date.

Every action item must answer three questions:

  1. What exactly will change? — name the alert, the runbook section, the circuit-breaker threshold, the test case.
  2. Who is the owner? — one person; committees do not ship.
  3. When is it done? — a specific date or sprint, not "soon".

Categorize by impact tier:

  • Prevent — eliminates the root cause (adds the missing guard, removes the dangerous code path).
  • Detect — closes the detection gap (adds the missing SLO alert, reduces MTTD).
  • Mitigate — reduces blast radius for the next occurrence (adds a kill-switch, improves rollback speed).

Track in the same system as engineering work (sprint backlog, issue tracker). Postmortem action items that live only in a doc rot and get forgotten.

Incident Metrics

Track over rolling quarters to surface trends, not just individual incidents:

  • MTTD (Mean Time To Detect) — gap between incident start and first alert. Feeds swe-workbench:principle-observability SLO work; high MTTD signals missing or miscalibrated alerts.
  • MTTR (Mean Time To Recover) — gap between detection and full mitigation. Feeds swe-workbench:principle-resiliency rollback and degradation work; high MTTR signals slow deploy pipelines or inadequate runbooks.
  • Repeat-incident rate — same root cause recurring within a quarter. The single strongest signal that action items are not being completed or are not addressing the right layer.

Review trends in retros, not just in individual postmortems. A rising MTTD means the observability investment is not keeping pace with system complexity.

When a Postmortem is Overkill

Not every incident warrants a full postmortem. Reserve the full process for:

  • Customer-visible impact lasting more than a few minutes (adjust threshold to your SLO tier).
  • Incidents that required escalation beyond the on-call engineer.
  • Any incident in the same root-cause class as a prior postmortem (repeat signal).
  • Incidents where the responder felt they were close to making a much larger mistake.

For minor incidents below this threshold, a lightweight 5-line "incident note" (what happened, what was done, follow-up if any) is sufficient. The overhead of a full postmortem can discourage reporting if applied indiscriminately.

Red Flags

FlagProblem
The postmortem names an individual as the root causeBlame, not analysis. The system allowed the action; the fix belongs in the system.
Action items have no ownerOrphaned tasks. Without an owner, no one ships.
Action items have no due datePerpetually pending. No due date means no accountability.
The doc was written more than a week after the incidentMemory has decayed; the timeline will be inaccurate and contributing factors will be missed.
"Human error" appears as a root causePremature stop. Ask why the error was possible; the answer is the real root cause.
The incident timeline has gaps longer than 30 minutes with no annotationResponders were working but not communicating; the timeline is incomplete.
Action items are not tracked in the engineering backlogPostmortem action items that live only in a doc get forgotten. Link every item to a ticket.
No "what went well" sectionAnchoring bias — teams that only record failures fail to reinforce behavior worth repeating.